GitHub - MartinRepo/SmartGrid: Implementation of some smart grid sheduling algorithms, with a visualization page.
Scheduling for Smart Grid
Authored by: @Martingale
Click here to visit demo site. Just try it. :D
Content
Core strategies for following algorithms
Feasible Graph
Fixed Parameter
Pseudocode as following
Input: a set of job J
Output: an optimal configuration of J
{bi} i=1...τ/2+1 ← the boundaries {0, 2, 4, 6, ..., τ}
{Di} i=1...τ/2 ← the windows where Di is bounded by bi (inclusively) and bi+1 (exclusively)
{Ci} i=1...τ/2 ← the collection of job sets where Ci is the set of jobs in Di
Tleft ← a configuration that labels all jobs j ∈ J to be not yet executed for i from 1 to τ/2 do
Tright ← ListConfigurations(Di, Ci)
Tleft ← ConcatenateTables(Tleft, Tright)
Tleft ← FilterTable(Tleft)
return any configuration in Tleft
Greedy
Job is assigned to the machine with the smallest number of jobs currently assigned.
Genetic
Regard a solution as an individual. Then through constant crossover mutations (crossover: crossing two schedules to generate a new schedule.
Mutation: randomly changing the position or time of a task within a feasible interval.).
It uses the fitness function (calculating peak cost) to decide which scheduling scheme is kept and which is filtered out.
Dataset Preview
There are 11 jobs, 6 windows, 7 boundaries.Their width(duration) and height(power cost) is adjusted
Simulation
Performance Comparison
Load function: Sum of jobs' height in per unit time t. 𝐿(𝑡) = ∑𝐽:𝑡 𝐻(𝑗)
Total cost
Total cost function: Total cost of the entire scheduling solution S. 𝐶𝑜𝑠𝑡(𝑆) = ∑ 𝐿(𝑡)^𝛼
Peak cost
Peak cost function: 𝐶𝑜𝑠𝑡(𝑆) = max(𝐿(𝑡))^𝛼
Running time
Every algorithm's running time.